Bally’s Chicago Adjusts Non-Gaming Construction Schedule Amid Video Gambling Dispute
Written by Amir Perry · Aug 11, 2026

Bally’s Chicago Adjusts Non-Gaming Construction Schedule Amid Video Gambling Dispute

Bally’s Chicago has slowed construction on major non-gaming portions of its $1.7 billion permanent casino and entertainment complex in the River West neighborhood, including the hotel, event facilities, and restaurants, because of an ongoing dispute with city officials over the potential expansion of video gambling terminals across Chicago. The decision affects approximately 1,500 union construction workers, while the casino itself remains on track for an early 2027 opening.
Background of the Host Community Agreement
The 2022 Host Community Agreement between Bally’s and the city established terms for the development, and company representatives cited violations of that agreement as the reason for the slowdown. Bally’s has indicated it is considering withholding a $4 million payment tied to the project milestones. Observers note that the dispute centers on the city’s handling of video gambling terminal expansion, which Bally’s maintains conflicts with commitments made during the original approval process.
Impact on Workforce and Timeline
Construction crews working on the hotel tower, meeting spaces, and dining areas have seen reduced activity in recent weeks, yet the core casino floor and gaming operations continue without interruption. Project managers have confirmed that the early 2027 opening date for the casino remains unchanged, and crews focused on gaming-related infrastructure continue at full pace. Union representatives have begun discussions with both Bally’s and city officials to address the employment effects on the 1,500 workers whose assignments have been paused or scaled back.
Data from project filings shows the permanent facility was always planned in phases, with gaming elements prioritized for revenue generation ahead of full entertainment offerings. Bally’s has stated that the current adjustments allow resources to stay concentrated on the casino portion while talks continue over video gambling terminals. City records indicate that applications for additional VGT locations remain under review, adn no final decisions have been issued as of the latest updates in August 2026.

Company Position and Next Steps
Bally’s has publicly referenced specific sections of the 2022 agreement that address competition from expanded video gambling within city limits, and the company maintains that those provisions have not been upheld. Officials from the project have outlined that the withheld $4 million payment would ordinarily support infrastructure improvements tied to the non-gaming areas. Negotiations between Bally’s representatives and city staff are scheduled to resume, with both sides reviewing documentation related to VGT approvals and the original community benefit terms.
Project timelines released by Bally’s show that the casino building envelope and internal fit-out for gaming spaces are advancing on schedule, while exterior work on the hotel and adjacent restaurant structures has been sequenced to follow resolution of the current disagreement. City planning documents confirm that permits for the gaming areas were issued separately, allowing that portion of construction to proceed independently of the hotel and event facilities.
Broader Context of Video Gambling in Chicago
Chicago’s approach to video gambling terminals has evolved since the state legalized the machines, and the city continues to evaluate new applications against existing regulations. Bally’s position in the dispute rests on the expectation that the Host Community Agreement would limit or coordinate any citywide expansion of VGTs near the River West site. Municipal records list multiple pending applications, and revenue comparisons between existing terminals and projected casino income have been referenced in ongoing discussions.
Construction updates filed with the city show that the overall project footprint remains intact, and Bally’s has emphasized that the slowdown is limited to non-gaming elements rather than a full project halt. Union leaders have requested regular updates on worker reassignments, and Bally’s has committed to maintaining communication channels during the negotiation period.
Conclusion
The dispute between Bally’s Chicago and city officials over video gambling terminal expansion has produced a targeted slowdown in non-gaming construction at the River West site, while the casino component stays on its early 2027 timeline. The situation involves approximately 1,500 union workers, a potential $4 million payment delay, and references to the 2022 Host Community Agreement. Both parties have indicated that talks will continue, with project records showing the gaming facilities advancing separately from the paused hotel, event, and restaurant portions.